Step 1

Feasibility Assessment / Site Visit

The service includes phone consultation, site visit to determine overhead crane clearance and truck accessibility, the review of the building location, orientation, foundation options, and site-specific requirements. It also includes budgetary estimates with regard to shipping, crane work and on-site installation. Lastly we make the design proposal.

    Step 2

    Design and Engineering

    Once the design proposal is approved we move on to create a 3D visual representation of your home where you can make revisions and finally approve. Then we create the drawings, Site plan, floorplans, elevations, sections, and initial foundation design.

    Step 3

    Permit Submittals

    Once all architectural, engineering, and certification documentation is complete, all drawings and accompanying documentation are compiled and can be submitted for Building Permits in the local planning office.

    Step 4

    40% Construction Down Payment

    Upon approval of the Building Permit from the planning office, we move on to the construction stage. A 40% Manufacturing Down Payment is necessary to be deposited prior to the manufacturing start date.

    Step 5

    Production and 30% Progress Payment

    At key stages of construction, we will provide updates and pictures of your home. Your local contractor begins site preparation and foundation work. The 30% manufacturing progress payment is due upon completion of the structural frame and prior to the start of Module complexing, Mechanical/Electrical/Plumbing rough-in, insulation, drywall, paint, and interior finishing.

    Step 6

    Completion of your Cocoonand 30% payment

    Upon completion of your Cocoon Module in our construction facility, the final 30% of the unit is due.

    Step 7

    Shipping, craneand installation payment

    30 days prior to the scheduled shipping date, we will re-quote and provide you with the updated shipping, crane and installation pricingPayment is due 15 days prior to the scheduled shipping date

    Step 8

    Delivery and Onsite Installation

    Once we confirm that your site is ready to receive your Cocoon, we then book the crane, trucks and send the Cocoon Modules team to your site. Once onsite, our team coordinates with the Crane Operator to land the individual modules onto the foundation and complete the installation. Site utilities are then connected to the home.

    Step 9

    Move in to your new house!

    Final walkthrough and keys given to you. You can now move in to your new house and enjoy the view!

    Step 1

    Feasibility Assessment / Site Visit

    The service includes phone consultation, site visit to determine overhead crane clearance and truck accessibility, the review of the building location, orientation, foundation options, and site-specific requirements. It also includes budgetary estimates with regard to shipping, crane work and on-site installation. Lastly we make the design proposal.

      Step 2

      Design and Engineering

      Once the design proposal is approved we move on to create a 3D visual representation of your home where you can make revisions and finally approve. Then we create the drawings, Site plan, floorplans, elevations, sections, and initial foundation design.

      Step 3

      Permit Submittals

      Once all architectural, engineering, and certification documentation is complete, all drawings and accompanying documentation are compiled and can be submitted for Building Permits in the local planning office.

      Step 4

      40% Construction Down Payment

      Upon approval of the Building Permit from the planning office, we move on to the construction stage. A 40% Manufacturing Down Payment is necessary to be deposited prior to the manufacturing start date.

      Step 5

      Production and 30% Progress Payment

      At key stages of construction, we will provide updates and pictures of your home. Your local contractor begins site preparation and foundation work. The 30% manufacturing progress payment is due upon completion of the structural frame and prior to the start of Module complexing, Mechanical/Electrical/Plumbing rough-in, insulation, drywall, paint, and interior finishing.

      Step 6

      Completion of your Cocoonand 30% payment

      Upon completion of your Cocoon Module in our construction facility, the final 30% of the unit is due.

      Step 7

      Shipping, craneand installation payment

      30 days prior to the scheduled shipping date, we will re-quote and provide you with the updated shipping, crane and installation pricingPayment is due 15 days prior to the scheduled shipping date

      Step 8

      Delivery and Onsite Installation

      Once we confirm that your site is ready to receive your Cocoon, we then book the crane, trucks and send the Cocoon Modules team to your site. Once onsite, our team coordinates with the Crane Operator to land the individual modules onto the foundation and complete the installation. Site utilities are then connected to the home.

      Step 9

      Move in to your new house!